Was this page helpful?

FPSC amendment

    Table of contents
    1. 1. Project

    TOC 

    Other pages:


    Project

     

    Project Leader: Bruno Gonçalves

     

    Project Objective

    •Adaptation and extension of the Fast Plant System Data Acquisition Prototypes (ITER_D_4HVBLJ) on 11/07/2011
    •Goals
    –Transform some of the previous delivered product “prototypes” into an ITER standard high quality products
    •ATCA PCIeswitch Card – more specifically the RTM PCIeHost Interface,
    •ATCA ADC module with the capability to operate either in chopper or in normal mode,
    •ATCA shelf with full-mesh interconnection,
    •MARTeframework integration preparation in CODAC Core System. The decision of integrating MARTein CODAC standard solutions is not acted for now. This step is a prerequisite for this decision,
    •FlexRIOEPICS ASYN device support for CODAC Core System V3
     
    Project specifications here
    The proposal presented to ITER can be found here
     
    Project Approach
    •Operating Environment
    –The products will operate on Red Hat Enterprise Linux 64-bits platform version 6
    –For real time requirements, a tuning on Red Hat MRG extension will be required.
    –The software environment and samples will be developed using Core System V2.1 distribution
    •3.0.beta?
     
    •Design and Implementation Constraints
    –The dependency between the products will be minimal in order to use each product in many different configurations.
    –For instance the software support of I/O modules should not rely exclusively on the MARTemodule which is only one specific use case.
    –Same remark applies for the FlexRIOEPICS ASYN support device that should not be dependant of any archive or communication system.
     
    •User Documentation
    –Final engineering and design documents will be delivered for each product as well as the installationand user manuals. For existing products (MARTe), current material could be referenced and the provided documentation could only focus on CODAC integration and usage.
    –The source code of each product will be organised according to CODAC standard file structure [IDM:33T8LW] and will be registered in CODAC SVN repository.
    –The project will be built and managed using the mvncommands: mvncompile, mvnrun, mvnstop and mvnpackage in order to produce RPM packages and ease the deployment process
     
    •Test Plan & Samples
    –A test plan will be produced for each product detailing the different scenarios with the expected results.
    –Sampleswill be produced to demonstrate the main functionalities of the product
    –A monitoring screen based on CSS BOY and EPICS will be developed allowing user interaction on an EPICS IOC sample.
    –The interface with the alarm server and the archive engine will also be demonstrated using CSS tools.
    –The user will be allowed to change EPICS standard thresholds such as noise reduction, monitor and archive dead bands
     
    •Assumptions and Dependencies
    –CODAC will propose a standardisation of FPGA Application Register Table and an abstract model for FPGA Asyndevice support which will be provided to implement FlexRIOdriver.
    –Open licensing model will be established for the products allowing all vendors to adhere and access blueprints and code according to the EURATOM licensing.
     
    Deliverables and Due Dates

    Milestone and

    Bidder Deliverables

    Dates

    (weeks)

    Location, Action and

    ITER-IO Deliverables

    Kick-off meeting

    T0 18/11/2011

    Meeting held at ITER IO premises.

    Minutes of Meeting.

    Delivery of the final Engineering Design Document

    T0+2 weeks

    These documents shall be delivered electronically.

    Review

    T0+4 weeks

    These documents shall be commented by ITER IO. The bidder shall incorporate comments in the next version.

    Review Report.

    Delivery of ICD and Test Plan

    Delivery of Production Plan (unit cost estimation)

    T0+5 weeks

    These documents shall be delivered electronically.

    Review

    T0+7 weeks

    These documents shall be commented by ITER IO. The bidder shall incorporate comments in the next version.

    Review Report.

    Delivery of the products with their engineering design documents, test plan and samples

    T0+12 weeks

    The products will be shipped to ITER IO.

    The code source and samples will be delivered in SVN.

    These documents shall be delivered electronically.

    Improvement of the product quality

    T0+30 weeks

    Iterative process. Integration of IO comments and submitted bugs.

    Monthly Bugs Report.

    Delivery of all final documentation and samples for the products

    T0+32 weeks

    Finalisation. 

    End of task

     

    Acceptance Criteria

    •Each product will be manufactured in small quantity early in the project – including hardware and software (Linux driver, EPICS device support, samples)

    •3 x ATCA PCIeswitch Cards,
    •2 x ATCA ADC modules,
    •1 x ATCA shelf with full-mesh interconnection specification,
    •1 x MARTepackage,
    •1 x FlexRIOEPICS ASYN package.
    •Each product will be tested by IO and other labs
    according to the delivered test plan
    •This is an iterative process in order to improve the product quality
     
    Project Management
    •Meetings
    Progress reports shall be submitted by IST every month
    Minutes of meetings and review reports, including action item lists, will be written by ITER- IO
    •Issue Management
    SharePoint site and actions tracking
    •Change Management
    •Risk Management
    –None 
     
    Internal Organization
    FPSC_Amendment_organigram.png
    Was this page helpful?
    Tag page (Edit tags)
    • No tags
    You must login to post a comment.
    Powered by MindTouch Core