Task
Task Leader: António Batista
–The ATCA ADC module as defined in
ITER_D_3ZH94Vwill be PICMG® 3.0/3.4 compliant and designed for high availability and reliability with easy hot-plug (connectivity on a passive RTM)
–The software support of the ATCA ADC product will be independent of MARTe
•In early phase, 2 x ATCA ADC modules will be shipped to CODAC onsite
Sub-Tasks:
1.1. Hardware
1.1.1. Boards delivery............................... T0 + 12 weeks (ATCA-IO-PROCESSOR prototype + RTM modified)
T0 + 32 weeks (ATCA-IO-PROCESSOR + RTM final versions)
1.1.2. Board test..................................... T0 + 12 weeks (ATCA-IO-PROCESSOR prototype)
T0 + 30 weeks (ITER debuging end)
1.2. Firmware
1.2.5. Firmware delivery............................ T0 + 12 weeks (ATCA-IO-PROCESSOR prototype)
T0 + 32 weeks (ATCA-IO-PROCESSOR final version)
1.3. Software
1.3.1. Linux Driver delivery........................ T0 + 12 weeks (ATCA-IO-PROCESSOR prototype)
T0 + 32 weeks (ATCA-IO-PROCESSOR final version)
1.3.2. EPICS Device Driver delivery .............. T0 + 12 weeks (ATCA-IO-PROCESSOR prototype)
T0 + 32 weeks (ATCA-IO-PROCESSOR final version)
1.3.3. Linux RPM Packaging delivery............. T0 + 12 weeks (ATCA-IO-PROCESSOR prototype)
T0 + 32 weeks (ATCA-IO-PROCESSOR final version)
1.3.4. Test software delivery...................... T0 + 12 weeks (ATCA-IO-PROCESSOR prototype)
T0 + 32 weeks (ATCA-IO-PROCESSOR final version)
1.3.5. IPMC.............................................T0 + 12 weeks (ATCA-IO-PROCESSOR prototype)
T0 + 32 weeks (ATCA-IO-PROCESSOR final version)
1.4. Documentation
1.4.1. Engineering Design document............. T0 + 12 weeks (ATCA-IO-PROCESSOR prototype)
1.4.2. Installation and User Manuals...............T0 + 12 weeks (ATCA-IO-PROCESSOR prototype)
T0 + 32 weeks (ATCA-IO-PROCESSOR final version)
1.4.3. Test Plan.........................................T0 + 5 weeks
1.4.4. ICD................................................T0 + 5 weeks (not delivered)
1.4.5. Production plan (unit cost estimation)....T0 + 5 weeks
1.5. Support
1.5.1. Whenever requested